Nr. | Milestone name | WP | Expected date [1] | Means of verification[2] | Status |
4.1 | Webpage for transnational access and scientific visits. | 4 | 2 | DONE | |
12.1 | Report describing the choice of isotopes to be measured in MINERVE and IRMM/n_TOF facilities and manufactured. | 12 | 6 | ||
11.1 | Cutting of samples in hot cell. | 11 | 9 | ||
3.1 | Report on the choice of the targets to be fabricated and equipment to be developed. | 3 | 12 | ||
8.1 | Completion of a list of target requirements for target preparation in CHANDA. | 8 | 12 | ||
8.2 | Completion of and commissioning of beam at nELBE-2, HZDR. | 8 | 12 | ||
12.2 | Report describing a MINERVE model to be used by participant for interpretation. | 12 | 12 | ||
12.3 | Report exposing the chosen integral benchmarks for uncertainty propagation. | 12 | 12 | ||
3.2 | Decision regarding the use of the requested funds for Activity 2 and their assignment to different partners. | 3 | 18 | ||
11.2 | Development of chemical separation systems. | 11 | 18 | ||
8.3 | Completion of and first beam at Experimental Area 2 (EAR-2) at CERN n_TOF. | 8 | 24 | DONE | |
8.4 | Completion of and first beam at Neutrons For Science (NFS) at SPIRAL2, GANIL. | 8 | 24 | ||
12.4 | Report on methodologies used to assimilate integral experiments. | 12 | 24 | ||
12.5 | Intermediate internal review of the study on new infrastructure and capacities. | 12 | 24 | ||
3.3 | Report describing the advancement of the fabrication of the new targets. | 3 | 26 | ||
10.1 | Summary report of available and new data for library validation. | 10 | 27 | ||
9.1 | Full quantitative control over the EXFOR database (NEA/IAEA), and automated procedures for evaluators to directly adopt experimental data in evaluations. | 9 | 36 | ||
9.2 | Standardized processing routes for European nuclear data libraries for all reactor codes of interest, especially the European ones (TRIPOLI, APOLLO, SERPENT, FISPACT). | 9 | 36 | ||
9.3 | Capability to perform exact uncertainty calculations for nuclide inventory. | 9 | 36 | ||
8.5 | Completion of a neutron-based fission fragment source at IGISOL. | 8 | 36 | ||
11.3 | Completion of the advanced experimental technique for full fragment identification. | 11 | 36 | ||
9.4 | A method to use Unified Monte Carlo or equivalent covariance method on a routine scale, extended to angular distributions. | 9 | 48 |
Nr. | Milestone name | WP | Expected date [3] | Means of verification[4] | Status |
3.1 | Report on the choice of the targets to be fabricated and equipment to be developed. | 3 | 12 | ||
3.2 | Decision regarding the use of the requested funds for Activity 2 and their assignment to different partners. | 3 | 18 | ||
3.3 | Report describing the advancement of the fabrication of the new targets. | 3 | 26 | ||
4.1 | Webpage for transnational access and scientific visits. | 4 | 2 | DONE | |
8.1 | Completion of a list of target requirements for target preparation in CHANDA. | 8 | 12 | ||
8.2 | Completion of and commissioning of beam at nELBE-2, HZDR. | 8 | 12 | ||
8.3 | Completion of and first beam at Experimental Area 2 (EAR-2) at CERN n_TOF. | 8 | 24 | DONE | |
8.4 | Completion of and first beam at Neutrons For Science (NFS) at SPIRAL2, GANIL. | 8 | 24 | ||
8.5 | Completion of a neutron-based fission fragment source at IGISOL. | 8 | 36 | ||
9.1 | Full quantitative control over the EXFOR database (NEA/IAEA), and automated procedures for evaluators to directly adopt experimental data in evaluations. | 9 | 36 | ||
9.2 | Standardized processing routes for European nuclear data libraries for all reactor codes of interest, especially the European ones (TRIPOLI, APOLLO, SERPENT, FISPACT). | 9 | 36 | ||
9.3 | Capability to perform exact uncertainty calculations for nuclide inventory. | 9 | 36 | ||
9.4 | A method to use Unified Monte Carlo or equivalent covariance method on a routine scale, extended to angular distributions. | 9 | 48 | ||
10.1 | Summary report of available and new data for library validation. | 10 | 27 | ||
11.1 | Cutting of samples in hot cell. | 11 | 9 | ||
11.2 | Development of chemical separation systems. | 11 | 18 | ||
11.3 | Completion of the advanced experimental technique for full fragment identification. | 11 | 36 | ||
12.1 | Report describing the choice of isotopes to be measured in MINERVE and IRMM/n_TOF facilities and manufactured. | 12 | 6 | ||
12.2 | Report describing a MINERVE model to be used by participant for interpretation. | 12 | 12 | ||
12.3 | Report exposing the chosen integral Benchmarks for uncertainty propagation. | 12 | 12 | ||
12.4 | Report on methodologies used to assimilate integral experiments. | 12 | 24 | ||
12.5 | Intermediate internal review of the study on new infrastructure and capacities. | 12 | 24 |
[1] Measured in months from the project start date (1st month).
[2] Show how you will confirm that the milestone has been attained. Refer to indicators if appropriate. For example: a laboratory prototype completed and running flawlessly; software released and validated by a user group; field survey complete and data quality validated.